Milestone | Date |
Design of Baseline Enterprise Architecture Complete | September 30, 2024 |
District Design Initial Draft | November 15, 2024 |
KDE Tenant Design Approval | December 13, 2024 |
Data Normalization Playbook (released) | December 15, 2024 |
Baseline Enterprise Architecture Complete | December 31, 2024 |
District Tenant Manifest Complete | December 31, 2024 |
Enablement Implementation Playbook (released) | January 31, 2025 |
Test Phase | February 10, 2025 - February 28, 2025 |
Prototype and POC Completion | March 1, 2025 |
Enablement Early Adopters | March 10, 2025 - April 11, 2025 |
District Rollout 25% Complete | June 30, 2025 |
District Rollout 50% Complete | September 30, 2025 |
District Rollout 75% Complete | December 31, 2025 |
District Rollout Complete | June 30, 2026 |
Transition to Managed Support | June 30, 2026 |